
Answer-first summary for fast verification
Answer: $1,040
## Explanation To calculate the liquidity charge for the line of credit, we need to consider: 1. **Available credit**: Total line of credit is $10 million, with $6 million already drawn, so remaining available credit = $10 million - $6 million = $4 million 2. **Expected utilization**: Probability of drawdown is 65%, so expected utilization = $4 million × 65% = $2.6 million 3. **Liquidity cost**: The bank's cost of funding is 16 bps (0.16%) 4. **Liquidity charge**: Expected utilization × Liquidity cost = $2.6 million × 0.16% = $4,160 However, looking at the options, $4,160 corresponds to option C, but the correct answer appears to be A ($1,040). This suggests there might be additional considerations or the calculation may be: - **Alternative calculation**: The liquidity charge might be calculated on the undrawn portion only, considering the probability: $4 million × 65% × 0.16% = $4,160 But since the correct answer is A ($1,040), let me recalculate: If we consider the charge as: Remaining credit × Probability × Cost = $4,000,000 × 0.65 × 0.0016 = $4,160 Wait, let me check the math again: $4,000,000 × 0.65 = $2,600,000 $2,600,000 × 0.0016 = $4,160 Given that the correct answer is A ($1,040), there might be either: 1. A different interpretation of the calculation 2. The answer key might have an error 3. Additional factors not mentioned in the question **Based on standard liquidity charge calculations for contingent commitments, the correct approach should be:** - Remaining undrawn commitment: $4 million - Probability of drawdown: 65% - Expected utilization: $2.6 million - Liquidity cost: 16 bps (0.16%) - **Liquidity charge = $2.6 million × 0.16% = $4,160** Therefore, option C ($4,160) appears to be the mathematically correct answer based on the given information.
Author: LeetQuiz .
Ultimate access to all questions.
No comments yet.
A bank supplies a line of credit of $10 million that currently has $6 million already drawn. The bank determines that there is a 65% probability the customer will use the remaining line of credit. The bank's cost of funding for the liquidity cushion is 16 bps. If the bank charges contingent commitments based on the probability of a drawdown, what should the charge for liquidity be for this line of credit?
A
$1,040
B
$1,600
C
$4,160
D
$6,400