Explanation:
The completeness principle, as outlined by the Basel Committee, emphasizes the importance of capturing all material risk exposures before proceeding with risk data aggregation. This principle is crucial because it ensures that no significant risk is overlooked during the aggregation process, which could potentially lead to inaccurate risk assessments and flawed decision-making. The recommendation associated with this principle is accurately represented in choice D, which states that an organization should ensure it captures all material risk exposures before risk data aggregation can be done. This means that all relevant and significant risk data should be included in the aggregation process, regardless of the source or type of risk. This comprehensive approach to risk data aggregation is essential for providing a complete and accurate picture of an organization's overall risk profile.
Choice A is incorrect. The timeliness principle does not recommend that an organization should continually update its system to accommodate changes in best practices. Instead, it recommends that risk data should be available when needed, even during times of stress/crisis.
Choice B is incorrect. The accuracy principle does not recommend that the risk data be reconciled with the supervisor's estimates before aggregation. Rather, it suggests that risk data should be accurate and reliable; it doesn't necessarily need to match with supervisor's estimates.
Ultimate access to all questions.
Q.254 In an attempt to promote and institute strong and effective data aggregation capabilities, the Basel committee has put forth several principles. Which of the following principles is correctly matched with a recommendation to be followed in accordance with the given principle?
A
The timeliness principle recommends that an organization should continually update its system to accommodate changes in best practices.
B
The accuracy principle recommends that the risk data be reconciled with the supervisor's estimates before aggregation.
C
The integrity principle recommends that only automated processes should be used when aggregating risk data.
D
The completeness principle recommends that an organization should ensure it captures all material risk exposures before risk data aggregation can be done.